About us
What we do
Useful links
News
ITC Level 1 Thermography Course ITC Level 1 Thermography Course

Construction



Construction of AES "Galabovo"

ÀÑÌ signs a new contract for implementation of scope electrical works for the Power Plant. The Contract covers the following electrical installation works: ACM1_AES-Galabovo.jpg

▪ Erection of new equipment - laying and connection of LV and MV cables, switchboards, circuit breakers, cable trays and pipes, grounding system;
▪ Erection works for 220êV equipment;
▪ Erection of cable racks;
▪ Erection of lighting and socket system;
▪ Manufacturing, supply and erection of switchboards: power distribution switchboards, direct current and local control switchboards;
▪ Control tests and commissioning of electrical equipment.













Construction of HPP "Momina Klisura" - 120MW


ACM2_mom_klisura.jpg















Construction and erection works at site Troyanovo-3 Mine East substation 110/20/6 kV

Contractor: Mini "Maritsa East" EAD - Radnevo
ACM3_troyanovo.jpg
Performed activities:
▪ 110 êV Open-yard switchgear – primary commutation;
▪ Erection of local, emergency and security lighting of 110 êV Open-yard switchgear;
▪ Delivery and Installation of new sections for 6,3 êV Indoor switchgear-1 and 6,3 êV Indoor switchgear-2 – primary commutation;
▪ grounding of star centre on 6,3 êV side;
▪ grounding system;
▪ battery;
▪ stabilized rectifier;
▪ MV panel AC and MV panel DC;
▪ auxiliary installations - lighting and power;
▪ secondary commutation.





Erection of a 110/20êV substation "Helios"
Contractor: National Electric Company EAD
ACM4_Substation_Helios_1.jpg
Performed activities:
▪ construction of Control Building;
▪ concrete foundations, and asphalt roads;
▪ installation, cabling and commissioning of all the electrical equipment.